Free Tool

PERT Calculator

Three-point estimate calculator for the PMP exam. Enter optimistic, most likely, and pessimistic values to get expected duration, standard deviation, variance, and confidence ranges instantly.

Enter Your Estimates

PERT Expected Duration (tE)
Standard Deviation (σ)
Variance (σ²)

Confidence Ranges

PERT Formula Explained for the PMP Exam

The PERT Expected Duration Formula

tE = (O + 4M + P) / 6

PERT (Program Evaluation and Review Technique) uses three estimates to calculate a weighted average. The most likely estimate (M) is weighted 4 times more heavily than the optimistic (O) and pessimistic (P) estimates. This creates a beta distribution that accounts for uncertainty while biasing toward the most probable outcome.

Standard Deviation

σ = (P − O) / 6

Standard deviation measures the spread of uncertainty in your estimate. A larger gap between optimistic and pessimistic means more risk. On the PMP exam, standard deviation is used with confidence ranges: ±1σ gives about 68% confidence, ±2σ gives about 95%, and ±3σ gives about 99.7%.

When the PMP Tests This

PERT questions on the 2026 PMP exam typically appear in two forms. First, straightforward calculations: “Given O=3, M=5, P=13, what is the expected duration?” Second, confidence range questions: “What range gives 95% confidence?” (answer: tE ± 2σ). Know both.

Common Exam Traps

Trap 1: Confusing PERT with triangular estimate. PERT = (O + 4M + P) / 6. Triangular = (O + M + P) / 3. The PMP tests both. Read which one the question asks for.

Trap 2: Variance vs. standard deviation. Variance = σ² (standard deviation squared). If the question asks for variance, square the standard deviation. Some questions give you activities on the critical path and ask for the total project variance — add the individual variances, not the standard deviations.

Trap 3: Adding standard deviations. You cannot simply add standard deviations across activities. You must add the variances, then take the square root to get the combined standard deviation. This is a frequent PMP exam trap for critical path duration confidence questions.

Want to practice PERT and three-point estimate questions with AI-powered explanations?
Try PM Mastery free — 100 questions included →

Master every PMP formula

4,500+ questions · AI Coach powered by Claude · PERT, EVM, and all formulas explained

Start Free →